Site icon UGA Today

EITS schedules Boyd Data Center maintenance

EITS will conduct maintenances on Feb. 24, March 23 and March 30 at the Boyd Data Center in efforts for the uninterruptible power supply system replacement.

During the Feb. 24 maintenance, building power will be shut down for the Boyd Graduate Building and McBay Science Library from 4-10 a.m. Boyd Data Center computer resources should not be impacted.

These will be the final phases of the project and will result in the desired upgrade to the Boyd Data Center’s uninterruptible power supply.

Key points for the upcoming maintenances:

Information Technology System Owners may elect to shut down non-essential systems in the Boyd Data Center during these maintenances. Information Technology System Owners who would like to request emergency cooling protocols for systems should contact Jeff Teasley at jteasley@uga.edu or Chris Fleming at cfleming@uga.edu.

Those who are aware of activities planned during these maintenance times and would like assistance with planning or have questions on these maintenance activities should contact Jeff Teasley at jteasley@uga.edu.

Additional details about this maintenance are available on the EITS website.